Progress over period (19/07/2019 – 08/08/2019)
- Structural demolition of existing ground floor slab
- On site crushing of hardcore resulted from demolition to minimise vehicle movement
- Breaking out existing foundations for piling works
- Installation of Temporary Works to support existing retaining works
- Excavations works
Actions over next period (08/08/2019 – 08/08/2019)
- Breaking out existing basement slab to allow piling
- Crush hardcore material resulted from demolition to minimise vehicle movement
- Create piling mat
- Create Pit Lane after Bus Stop has been suspended
- Park Land area if licence is granted